Project Updates

March 3, 2010

On Bunnell Road, they will be placing sod around the McNeil pond area this week. They are progressing towards Eden Park and Bunnell with road tie-ins so they can shift traffic soon.

They are also continuing preparing for curb work and stabilizing for Bunnell road work towards Eden Park. When the next portion of paving is scheduled, it will be posted here.

Eden Park still has pipe work being done, which they are finishing up soon then they will resume road work.

Please drive slowly through the construction areas and pay attention to the workers and equipment that may be near the road and sidewalks. All traffic shifts will be flagged and indicated with signs and cones.

We understand that questions do come up. So, if you have any questions or require information give us a call or send a comment on the "Contact Us" page..

February 17, 2010

On Eden Park, the storm pipe work is continuing and progressing towards Maitland Boulevard.

On Bunnell, they are preparing for curb work and stabilizing for road work towards Eden Park. When the next portion of paving is scheduled, it will be posted here.

Please drive slowly through the construction areas and pay attention to the workers and equipment that may be near the road and sidewalks. All traffic shifts will be flagged and indicated with signs and cones.

We understand that questions do come up. So, if you have any questions or require information give us a call. We will be happy to meet with you and explain the project. Please contact us, at 1-321-288-0318 or 1-407-293-2412 and we will be happy to answer your questions or set up a meeting with you. You can also submit a comment to us via email by clicking here and filling out the form..